The Construction Organization Plan Research On Pollution Treatment Engineering Project Of Water Source In Jilin Province

Posted on:2016-06-27Degree:MasterType:Thesis
Country:ChinaCandidate:Z Q ZhangFull Text:PDF
GTID:2181330467481514Subject:Integrated Project Management
Abstract/Summary:PDF Full Text Request
As one of the pillar industries of the national economy, the construction industryis facing an increasingly complex and volatile external environment and intensecompetition; as the management of the core construction industry, the difficulty ofproject management is also increasing. From the beginning Lubuge promotionexperience, our modern project management has been gradually developing anddeepening reform.In contemporary project management plan, organize, coordinate and control thefour most important functions is to manage the project management controls arespecific measures to ensure the implementation of the project plan. Adequateplanning for the implementation of the project has laid a solid foundation, so that itcan better control to ensure the project is not on track to ensure that the project onschedule, according to quality. Today, large-scale water conservancy projects andincreasingly complex, making the importance of project planning and control ofincreasingly prominent. At present, in the Jilin area, the level of awareness of newtechnology to learn project management is not high enough, the use is also notflexible enough. Builders door or older with experience too much work, too much useof old construction techniques for planning and control for the entire project.Excessive reliance experiences ignore advanced theoretical study and practicalapplication.Based on this background of this new legislation into Reservoir Authority, waterpollution control project as a case study for the construction enterprise project management process planning and control environment. Describes a variety of newtechnologies from basic gratitude to start, combined with the local climatecharacteristics. For the proposed use of new technology project management bothbefore and after the construction organization plan benefit analysis and summary. Atthe same time improving the process also incorporates some of the practicalapplication of project management techniques. Sources theory and practice, theperfect combination of theory and practice in order to create the perfect project.Firstly, the basic overview of Changchun new legislation into the reservoir,combined with water conservancy construction control research theory, the waterconservancy construction control philosophy from the perspective of control theory,and the establishment of a theoretical framework for the construction of the specialgeographical conditions. Around the water conservancy project construction processand characteristics of the two dimensions of time and money for analysis of waterconservancy and hydropower construction system. And on this basis, proposes a newmethod for controlling water conservancy construction. The theory for waterconservancy construction process can drive dynamic control of water provide a newtheoretical research ideas.Secondly, and climatic conditions and meteorological data for the regionChangchun, Jilin Province for the construction organization of water pollution controlproject design improvement. Analysis of the individual projects in the process ofmulti-objective control integrated mechanism, thought control based on the individual.Meanwhile, from the perspective of cybernetics proposed model adaptive real-timefeedback strategy and tactics, the use of creating a network diagram and Gantt charts,etc., duration and investment cycle contrast works old and new constructionorganization plan two actual comparative analysis. The original design of theproposed construction of organizational problems exist. Help solve a trap on the pathof development of enterprises. Again for the question raised by the control analysis. Systematic analysis of thecomplex relationship between the constraints of the subsidiary project of waterconservancy projects, combined with engineering management techniques forcoherent female construction design flow of water pollution control projects to bemodified. Which use a Gantt chart to see the true problem set period, comparativeanalysis of critical path logic get out immediately before and after the close. Networkdiagram above a specific coordinate adjustment construction steps in the rationality ofconstruction organizations with demonstrated statistically improved engineeringdesign. After optimization of the proposed theoretical basis and technical support, aswell as take advantage of the time value of money in comparison to the cost savingsverification.Finally, a specific solution, just change the original construction design, andstatistical sums up the value of the economic benefits of new construction design andfinally brought to the project.
Keywords/Search Tags:Project management, The construction organization design, The construction ofwater conservancy, The design and construction of adjustment
PDF Full Text Request
Related items