The Research On Construction Management And Key Construction Technology In Miaojiaba Hydropower Station

Posted on:2011-08-22Degree:MasterType:Thesis
Country:ChinaCandidate:Y N FanFull Text:PDF
GTID:2132360305470351Subject:Hydraulic engineering
Abstract/Summary:PDF Full Text Request
The water and electricity project's construction is an investment scale is big, the construction cycle long, involves the specialized systems engineering. The construction process is carries on the design paper the transformation the process. Regarding the water and electricity architectural engineering, constructs this stage in the project, the consumption manpower, the physical resource, the financial resource are most, condition restrictions and so on social politics, economy, management, technology is been biggest, the natural terrain, the geology, the hydrology, the meteorological condition influence is been broadest, the contradiction is most intriguing. Therefore, when project implementation carries on the comprehensive construction organization management and the main construction technique research, has the very significant technical economy significanceThe Bailongjiang River Miaojiaba hydroelectric power station concretes kneading board rock-fill dam construction mainly includes the base of dam, the side slope to excavate and the supports and protections project, the concretes kneading board rock-fill dam reclamation work, the foundation treatment project, the principal river bed cut-off project, the upstream and downstream coffer dam reclamation and the anti-seepage project, the river bed overburden layer concretes cut-off wall project, the seedling village expels flood water the project as well as other near constructs the facility and so on. The construction time tight is the subject matter which in the construction faces. Through the science organization management, selects the advanced construction technique, to cause the entire project the construction process to be smooth, but order. During guarantee construction progress, but must establish the perfect quality surveillance and the management system. Through the strict management and the control, enable the construction quality also to obtain the guarantee.In the past, because (i.e. time question) and the reasonable construction organization did not manage the enough value to the construction progress, thus caused some engineering construction "the time to be long, the construction cost was high, the benefit was bad" question. Through to this topic's research, provides the further for engineering project's implementation the scientific basis, through to engineering project's construction technique plan and the construction organization management and the main construction technique research, promotes economic prosperity by the time, benefits the society.
Keywords/Search Tags:Miaojiaba hydroelectric power station, Concrete faced cemented-rockfill dam, Roller compaction, Construction management, Construction technology
PDF Full Text Request
Related items