This article mainly through the use of the theory and method of project management,for the first qian company 2 million t/a coking dynamic compaction method of foundation treatment project of the project schedule plan and schedule control method research.Including starting from project bidding,project implementation and the preparations for the former,the dynamic compaction construction parameters,dynamic compaction method of foundation treatment,dig the fill slope construction,the intensity of greening construction,finally all through the project to complete the final acceptance of the process.The experimental method used in the study,literature research,quantitative analysis and qualitative analysis,case study method,etc.The concrete research content includes the following four aspects:(1)Dynamic compaction method first qian company foundation treatment project analysis of the status quo and existing problems.This part mainly through to the first qian company currently on the implementation of the dynamic compaction method of foundation treatment project and analysis to find out the existing problems and puts forward improvement scheme,and then defined the direction of next improvement.(2)To apply project management knowledge and methods of the 2 million t/a song qian company coking dynamic compaction method of foundation treatment project.First qian company through system analysis on the construction of dynamic compaction method of foundation treatment project,according to the project characteristic and the implementation of the project scope,the establishment of a specialized project headquarters,then the project decomposition according to the requirements of project management,so as to complete the first 2 million t/a coking company in guizhou construction of foundation treatment project of the dynamic compaction method.(3)Prepare the project schedule.Key research first qian company 2 million t/a coking foundation treatment project work breakdown structure,the dynamic compaction method based on work breakdown figure to estimate time limit,combined with the total construction period adjustment,finally determine the project time limit for a project,to complete the project schedule planning.This part will use the gantt charts,milestone plan project management tools,such as for said project schedule.(4)Suitable for the objective of the project schedule planning control method.According to complete the project schedule,and work breakdown structure,and develop a plan of the project schedule control process,the node from milestone plan control,schedule control point setting,etc is analyzed,and from the organization,management measures,technical measures,economic measures in four aspects,such as the progress of the detailed planning control measures,strengthen to the project schedule control.Finally through to the first 2 million t/a coking company qian to study the dynamic compaction method of foundation treatment project schedule management,with a range of targeted and guiding significance of conclusions.Subsequent project construction to provide the reference to the first qian company,as well as other Custer landform areas foundation treatment project implementation has reference and popularization significance. |