| This research is based on the specific work experience of QH telecom settlement system in the process of construction project management,and the project work is decomposed in detail for the specific tasks of the project,and finally the project has reasonable control in the progress management.First of all,this paper briefly introduces the basic situation of QH Telecom integrated settlement system construction project,including the project implementation background,project overall goal and result.At the same time,the characteristics of QH Telecom settlement system construction project progress analysis,and the study of the project progress control the practical significance of a detailed analysis.Combined with the purpose of this paper,the relevant theory and research status were sorted out,summed up the QH Telecom integrated settlement system construction project progress control research institute need to use the specific method.Secondly,this paper is based on the WBS QH Telecom integrated settlement system construction project progress management method.The use of WBS to define the project,decomposition,duration and other work,and to develop QH telecommunications settlement system construction project progress network diagram and the key line,on this basis,based on the WBS schedule preparation of the QH Telecom Integrated Settlement System Construction Project Schedule and Schedule Management Measures.Finally,this article has carried on the comprehensive summary,and has put forward the research insufficiency.Based on the research on the progress management of QH Telecom integrated settlement system construction project,this paper not only ensures the efficient and smooth development of the comprehensive settlement system,but also provides some reference value for the similarity of the settlement project project. |