Research On The Problems And Countermeasures In The Approval Process Of Local Government Engineering Construction Projects

Posted on:2022-08-01Degree:MasterType:Thesis
Country:ChinaCandidate:X L SongFull Text:PDF
GTID:2516306323483934Subject:Public Management
Abstract/Summary:PDF Full Text Request
At present,our country is in the phase of rapid economic growth,the growth of the economy can produce without specific benefits of high quality project,for better service project can more quickly complete the construction task,the government is focus on the implementation of construction projects in every region of the administrative examination and approval system reform,optimize the engineering construction project examination and approval,implement and decentralization,comprehensive optimization business environment.For a long time,the engineering construction project examination and approval matters for examination and approval process takes time,usually in series and the lack of connectivity between information system of examination and approval,attaches great importance to the advance approval ignore things afterwards regulation,intermediary service is not standard,the standard of examining and approving,makes the engineering construction project in the process of examination and approval for examination and approval of inefficient,slow down the progress of the construction projects be born,can raise the cost of enterprise and government,restricted the development of social economy.Although the reform of administrative examination and approval of engineering construction projects has achieved good results in recent years,there are still some weak links in the examination and approval process.It is necessary and urgent to study the problems existing in the examination and approval process of engineering construction projects and the countermeasures.This article R city L area,for example,around the engineering construction project examination and approval of local government,the analysis of existing problems and countermeasures in the process of using the theory of government process reengineering and service-oriented government,through the analysis of the status quo,finding problems,analyzing reasons,puts forward the overall train of thought,on some important is closely related to the research on the basis of literature review,The results obtained in the process of engineering construction project examination and approval are summarized.The administrative examination and approval items are thoroughly sorted out,the preconditions of examination and approval are reduced,application materials are simplified,the examination and approval items are standardized,the acceptance standards are unified,parallel examination and approval are implemented,the stages of approval are reasonably divided,the drawing examination and acceptance are jointly examined and accepted,and "parallel examination and approval are completed within a limited time".Implement the acceptance of tolerance and acceptance of shortage and credit commitment system for examination and approval.The examination and approval should be carried out first,followed by the completion of materials,greatly shortening the examination and approval time limit and improving work efficiency.Through interviews and other methods,the problems existing in the approval system,approval authority,approval process,approval supervision,approval platform and approval concept were summarized,aiming to find ways to optimize the approval of local government construction projects,improve approval efficiency and shorten approval time.From the authority for examination and approval of reengineering,model reconstruction of examination and approval,examination and approval platform reengineering,supervision for examination and approval of reengineering and approval concept reengineering aspect puts forward related Suggestions,including the power of examination and approval of from top to bottom and matters of devolution,implementing the standard of administrative examination and approval matters of carding,implementation of administrative examination and approval by web,intermediaries credit system construction,set up the demand oriented service consciousness,etc.,Realize the optimization and reengineering of the examination and approval process,and conduct the examination and approval of engineering construction projects in a scientific,reasonable and efficient way.R,L area of administrative examination and approval service as a product of relatively concentrated administrative reform,undertakes the important mission of administrative examination and approval system reform,the administrative department for examination and approval of the engineering construction project for examination and approval of the reality investigation and research,reform of administrative examination and approval for the engineering construction projects to provide a more complete,complete samples,It will have a positive effect on the optimization of the approval process of other local government construction projects,and also help to make up for the shortage of relevant theoretical research.The research on the approval of construction projects of the Bureau of Administrative Examination and Approval Service can effectively enrich the relevant theoretical research and the material library for the reform of the administrative examination and approval system of construction projects,and provide a reference basis for optimizing the administrative examination and approval of construction projects with The Times.
Keywords/Search Tags:Construction Project, Administrative Examination and approval, process reengineering
PDF Full Text Request
Related items