Font Size: a A A

Since The Comprehensive Transformation Of110kV Substation Engineering Solutions

Posted on:2015-12-14Degree:MasterType:Thesis
Country:ChinaCandidate:H ChenFull Text:PDF
GTID:2272330467470057Subject:Electrical engineering
Abstract/Summary:PDF Full Text Request
To the substation put into operation in1986, the running time is28years,although carried out in the years running through several technological transformation,but are only a small part of tinkering, not carried out large-scale transformation.According to the current load and xiangtang region (in2011has reached60MW)growth trend is expected in2015will reach101MW, the two35MVA of the maintransformer has been unable to meet the load demand in the region, the maintransformer must expansion. Were not designed to be integrated automation of changeearly in the design and several technological transformation, leading to the substationstatus quo is: not monitor equipment operating conditions, the operation can not beperformed remotely, you must send duty and so on.According to the current operating conditions of change, elaborated to theoverall design of comprehensive change and organizational design since therenovation project, focusing on the selection of variants to a need to transform thecontents of secondary equipment, and related equipment check. And detailedpreparation of construction plans and programs load transfer substation renovationproject.
Keywords/Search Tags:integrated automation, transformation plan, Construction Management
PDF Full Text Request
Related items