Schedule Management Of Simulation Training System Development In Datang (Chifeng) Renewable Power Co., Limited

Posted on:2016-08-13Degree:MasterType:Thesis
Country:ChinaCandidate:J C ZhaiFull Text:PDF
GTID:2309330467997885Subject:Project management
Abstract/Summary:PDF Full Text Request
In the last few years, as the increasingly serious environmental pollution causedby a large amount of exhaust gas produced in coal combustion, the excessiveconsumed of the traditional non-renewable energy, the gradual shortage of the coal,the government support and encourage renewable energy development andconstruction strongly. The wind power generation industry has developed rapidly inthese years in China, but the number of the related professional training can’t meetthe needs of wind power industry development. Therefore, Datang(Chifeng)Renewable Power Co., Limited intend to develop simulation training system by newtechnology to improve the technical level of wind practitioners, shorten the trainingcycle, improve the quality of training and create economic value. This thesis researchhow to manage simulation training system effectively to Ensure project schedule andmeet the design objectives.According to the actual situation, the paper analyze the development needs ofDatang(Chifeng)Renewable Power Co., Limited of the simulation training systemsystematically, and determine the key technology according to all the requirements,and study and solve all questions probably appeared. In order to allocate time,personnel, capital, technology and other important resources effectively, control theoverall progress, avoid the confusion, low efficiency, personnel communicationdisorders and other practical difficulties which may occur in the process of project,according to the needs and matters needing attention of the whole project, it carrieson the science of work breakdown structures, which called WBS, and with whichdetermine the division of the various tasks according to the different types of projectdevelopment, and implement the functions, responsible for personnel and theirrespective responsibility assignment matrix table mapping system development project.In order to ensure the project can proceed as scheduled, we use the ProjectEvaluation and Review Technique(PERT) to manage and control the whole projecttime limit for a project. Combining the reality of simulation training systemdevelopment project, arrange the order of work reasonably, draw project networkdiagram, find out every work on the key chain and calculate the overall time limit forthe whole project.In the process of the development, we pay attention to themanagement of each work on the key chain. The thesis devise the coding further,which take up the most time for the project, determine time node of each work tocontrol the limit effectively. In the process of project,we should be ready to resist thechange of needs, personnel, technology and capital to avoid affecting the whole time.Combined with the actual construction of the project, improve and perfect thesecurity work of the project, grasp the factors carefully, analyze the safeguards fromthree aspects, that is the personnel training and introduction, capital controls andsound system, in order to ensure the project schedule management smoothly.The objective of the project management is to assist the managers to completethe project efficiently by the scientific method, the effective combination of resourcesand the orderly connect of all stages. It will offer ideas and experiences for thebuilders type of construction management by researching the Schedule Managementof Simulation Training System Development in Datang(Chifeng)Renewable PowerCo., Limited.
Keywords/Search Tags:Simulation training system, Schedule management, Work Breakdown Structure
PDF Full Text Request
Related items